In Serta Simmons Bedding
LLC v. Casper Sleep Inc., [2019-1098, 2019-1159] (February
13, 2020), the Federal Circuit vacated the district court's
summary judgment of non-infringement and remanded with instructions
to enforce the settlement agreement that the parties made prior to
the grant of summary judgment.
Casper filed three motions for summary judgment on the issue of
non-infringement. While these motions were pending, the parties
executed a settlement agreement and filed a Joint Notice of
Settlement and Motion to Stay, informing the district court that
they "entered into a Settlement Agreement" and were
requesting that all deadlines be stayed. Two days later, the
district court granted summary judgment for Serta.