Happy New Year to all readers of the Insurance and Reinsurance
Disputes Blog. In this first post of the new decade, we find the
Ninth Circuit affirming a grant of summary judgment in favor of a
marine insurer after a fire destroyed a yacht. Unambiguous policy
provisions prevailed.
In Certain Interested Underwriters
at Lloyd’s, London v. Bear, LLC., No. 18-55668 (9th
Cir. Dec. 31, 2019) (Not for Publication), the corporate owner of a
yacht purchased an all-risks marine insurance policy. The policy
had what the parties called a Repair Clause. The clause required
that before the owner had the yacht undergo major repairs or
“not work” or when the yacht was in a shipyard that
requested a waiver of subrogation, the owner had to obtain the
insurer’s prior agreement. According to the court, the fire
was caused by hot work performed on the yacht as part of a major
repair at a shipyard that asked the owner for a waiver of
subrogation. The owner never obtained or attempted to