Share on LinkedInShare on LinkedIn

ARTICLE · 16 AUGUST 2018

"Workin' Nine To Five" – But Not In A Government Office: Requesting A Debriefing

Morrison Foerster
Morrison Foerster
Contributor
Morrison Foerster

Morrison Foerster

With approximately 1,000 lawyers in 19 offices, Morrison & Foerster is a preeminent global law firm...

View firm profile
Explore more from Morrison Foerster

In Exceptional Software Strategies, Inc., B-416232, the Government Accountability Office (GAO) recently addressed the obscure rules for when a disappointed offeror must request a debriefing.

United StatesGovernment, Public Sector

In Exceptional Software Strategies, Inc., B-416232, the Government Accountability Office (GAO) recently addressed the obscure rules for when a disappointed offeror must request a debriefing. It's generally well known that, in procurements where offerors may have a right to debriefings, a disappointed offeror must submit a written request to the contracting officer within three days after receipt of written agency notice that the company's proposal has been excluded from the competitive range. FAR 15.505(a)(3). If an offeror misses the deadline, it does not necessarily mean it won't get a debriefing, but any debriefing will not be "required."

Background

In Exceptional Software, on Thursday, March 15, the National Security Agency (NSA) provided the protester with written notice that its proposal was excluded from the competitive range and provided a brief rationale for that exclusion. Under FAR 15.505(a)(3), the offeror then had three days – until Monday, March 19