ARTICLE · 29 OCTOBER 2020

Government Contracts: Company's Key Personnel Rendered "Unavailable" Because Of Denied Security Clearance

Jones Day
Jones Day
Contributor
Jones Day

Jones Day

Jones Day is a global law firm with more than 2,400 lawyers in 40 offices across five continents....

View firm profile
Explore more from Jones Day

The U.S. Government Accountability Office ("GAO") recently sustained a bid protest concluding that a company was ineligible for award because of "key personnel unavailability."

United StatesGovernment, Public Sector

In Short

The Situation: The U.S. Government Accountability Office ("GAO") recently sustained a bid protest concluding that a company was ineligible for award because of "key personnel unavailability." Although the employee remained employed by the company and was willing to work on the contract, he had been denied a security clearance needed to perform the key position.

The Result: If a company has actual knowledge that a key person will not be able to perform the duties of the key position, the company has an obligation to inform the agency of the unavailability of its proposed key personnel. In such situations, the agency must either reject the proposal as unacceptable or open discussions to allow the offeror to revise its proposal.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from