Ensuring payment in the context of a termination for
convenience settlement can be a complicated process for primes and
subcontractors. A recent decision from the U.S. Court of
Appeals for the Federal Circuit, Parsons Global Services.,
Inc. v. Secretary of the Army, No. 2011-1201,
slip. op. at 12 (Fed. Cir. Apr. 20, 2012), reminds government
contractors that before a contractor may file a claim under the
Contract Disputes Act ("CDA") for the
government's failure to pay a routine request for payment, the
claim must be disputed. The decision in Parsons Global
Services highlights the practical complexities that face
a prime and a subcontractor in negotiating settlements resulting
from the government's termination for convenience. It
also serves as a reminder that the jurisdictional prerequisites for
filing a claim under the CDA may serve as a trap for unwary
contractors that fail to follow proper procedures in submitting
what is initially a routine request for payment.