Boards Of Contract Appeals Will Prod Contracting Officers To Issue Final Decisions

Some contractors elect to do nothing and wait out the CO, although this isn't necessarily a good option.

United StatesGovernment, Public Sector

David S. Black is a partner in the Tysons office and William M. Pannier is senior counsel in Los Angeles office.

The Armed Services Board of Contract Appeals (ASBCA) recently demonstrated that it is willing to help government contractors who are waiting many months for a contracting officer to issue a final decision on a pending certified claim.

As background, the government contract claims process is supposed to be efficient, providing for the "informal, expeditious, and inexpensive resolution of disputes," as the Contract Disputes Act (CDA) states.  See 41 U.S.C. §§ 7101-7109.  But that's easier said than done.  All too often, when a contractor submits a written request for equitable adjustment (REA) or certified claim, the Contracting Officer (CO), for whatever reason, doesn't "expeditiously" issue a final decision.  Sometimes, it may seem that the government is just sitting on the claim, without giving it due consideration at all.  What's a contractor to do