On June 30, 2011 the final FAR contract closeout rule will go
into effect.1 Although the Federal Register
notice accompanying the final rule states that it sets forth
"procedures for closing out contract files," the real
impact of the rule will be on a contractor's annual incurred
cost proposal. The final rule is a significant victory for the
Defense Contract Audit Agency (DCAA) insofar as it authorizes the
positions DCAA has advanced for years without previously having a
regulatory basis to do so.
A regulatory definition of what constitutes an
"adequate" incurred cost proposal
All cost-type contracts are required to include FAR 52.216-7,
"Allowable Cost and Payment." The clause sets out the
process for preparing indirect cost rates and requires that
contractors submit their annual incurred cost proposal within six
months of the close of their fiscal year. DCAA then audits that
proposal and eventually the contractor and the government reach an
agreement on final