A Wolf In Sheep's Clothing: The Final FAR Contract Closeout Rule

On June 30, 2011 the final FAR contract closeout rule will go into effect.

United StatesGovernment, Public Sector

On June 30, 2011 the final FAR contract closeout rule will go into effect.1 Although the Federal Register notice accompanying the final rule states that it sets forth "procedures for closing out contract files," the real impact of the rule will be on a contractor's annual incurred cost proposal. The final rule is a significant victory for the Defense Contract Audit Agency (DCAA) insofar as it authorizes the positions DCAA has advanced for years without previously having a regulatory basis to do so.

A regulatory definition of what constitutes an "adequate" incurred cost proposal

All cost-type contracts are required to include FAR 52.216-7, "Allowable Cost and Payment." The clause sets out the process for preparing indirect cost rates and requires that contractors submit their annual incurred cost proposal within six months of the close of their fiscal year. DCAA then audits that proposal and eventually the contractor and the government reach an agreement on final

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from