ARTICLE · 23 JULY 2013

Seventh Circuit Presents Statute Of Limitations Roadblock For Future PSD Enforcement Matters

In a recent case, the U.S. Court of Appeals for the Seventh Circuit ruled that the failure to obtain a prevention of significant deterioration construction permit under the Clean Air Act is not a "continuing violation" and, therefore, any government PSD claim based on the CAA must be filed within the five-year statute of limitations. No. 12-1026, 12-1051.

United StatesEnvironment

On July 8, 2013, in United States v. Midwest Generation, et. al, the U.S. Court of Appeals for the Seventh Circuit ruled that the failure to obtain a prevention of significant deterioration (PSD) construction permit under the Clean Air Act (CAA) is not a "continuing violation" and, therefore, any government PSD claim based on the CAA must be filed within the five-year statute of limitations. No. 12-1026, 12-1051 (7th Cir.). According to the court, the statute of limitations begins to run "when construction commences without a permit in hand."

The Seventh Circuit joins the Eighth and Eleventh Circuits in narrowly construing the statute of limitations for PSD claims. This ruling significantly affects the Environmental Protection Agency's (EPA) future PSD enforcement initiatives in the Seventh Circuit, and will require the EPA to file its claims (or sign a tolling agreement) within five years of a facility beginning construction without a PSD permit. It may also affect

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from