The uncertain and often lengthy time to get permitting decisions is always near the top of the list of industry complaints.

United StatesEnvironment

The uncertain and often lengthy time to get permitting decisions is always near the top of the list of industry complaints. Section 165 of the Clean Air Act provides some relief by requiring certain permit decisions to be made within one year. Last week, in Avenal Power Center v. EPA, District Judge Richard Leon, in what may comfortably be described as a strongly-worded opinion, held that EPA may not circumvent the one-year limit on permit decisions by carving out from the one-year period the time spent by the Environmental Appeals Board reviewing EPA's permit decision.

In March 2008, Avenal Power filed an application for a PSD permit necessary to construct a new gas-fired power plant in the San Joaquin Valley in California. When EPA had not issued a decision within two years, Avenal sued. In February 2011, Gina McCarthy, head of EPA's air office, announced that EPA would issue a permit decision by May 27, 2011. However, Judge Leon found EPA's commitment to be

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from