On December 19, 2019, the Federal Energy Regulatory Commission (FERC) disrupted the holiday season for many in the U.S. energy sector by issuing an order requiring PJM Interconnection

United StatesEnergy and Natural Resources

On December 19, 2019, the Federal Energy Regulatory Commission (FERC) disrupted the holiday season for many in the U.S. energy sector by issuing an order requiring PJM Interconnection (PJM) to amend its Minimum Offer Price Rule (MOPR) to expand restrictions on the participation of all state-subsidized resources in the PJM capacity market.  With PJM's March 18, 2020 filing in compliance with that order now on the books at FERC, the real implications of that MOPR order are becoming more clear.1

The MOPR was originally established in 2007, setting a floor price for resources bidding into PJM's capacity market to prevent them from deliberately underbidding to artificially suppress capacity prices, but has historically been applied only to new natural gas generation.  FERC's expansion of the MOPR to apply to all resources receiving state subsidies means that a whole new set of market participants may be subject to minimum price floors in bidding into PJM's capacity

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from