On December 19, 2019, the Federal Energy Regulatory Commission
(FERC) disrupted the holiday season for many in the U.S. energy
sector by issuing an order requiring PJM Interconnection (PJM) to
amend its Minimum Offer Price Rule (MOPR) to expand restrictions on
the participation of all state-subsidized resources in the PJM
capacity market. With PJM's March 18, 2020 filing in
compliance with that order now on the books at FERC, the real
implications of that MOPR order are becoming more
clear.1
The MOPR was originally established in 2007, setting a floor
price for resources bidding into PJM's capacity market to
prevent them from deliberately underbidding to artificially
suppress capacity prices, but has historically been applied only to
new natural gas generation. FERC's expansion of the MOPR
to apply to all resources receiving state subsidies means that a
whole new set of market participants may be subject to minimum
price floors in bidding into PJM's capacity