The US Court of Appeals for the First Circuit has affirmed the dismissal of two additional legal challenges to the Vineyard Wind 1 Project (the Project). On December 5, 2024, a First Circuit panel issued a consolidated.

United StatesEnergy and Natural Resources

The US Court of Appeals for the First Circuit has affirmed the dismissal of two additional legal challenges to the Vineyard Wind 1 Project (the Project). On December 5, 2024, a First Circuit panel issued a consolidated opinion in Seafreeze Shoreside v. DOI and RODA v. DOI1 affirming the Massachusetts District Court's decisions to grant summary judgment in favor of the federal government in two underlying cases challenging the Project's federal permits. The court's opinion marks the second time the federal government has successfully defended its approval of the Project in the First Circuit.2 The Project is currently under construction offshore Martha's Vineyard, Massachusetts, and is scheduled for completion in early 2025. Once complete, the Project will be capable of generating up to 800 megawatts of renewable energy.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from