ARTICLE · 23 OCTOBER 2026

Venture Global Update: Galp Prevails In Latest LNG Commissioning Dispute

Bracewell LLP
Bracewell LLP
Contributor
Bracewell LLP

Bracewell LLP

Paris is a vital energy hub in Europe, and our Paris office plays a central role in helping address...

View firm profile
Explore more from Bracewell LLP

An ICC tribunal has ruled in favor of Galp in its dispute with Venture Global over the Calcasieu Pass LNG facility, finding that Venture Global breached its obligation to declare the facility operational in a timely manner. This decision adds to a series of contrasting outcomes in similar disputes involving other buyers, with damages yet to be determined in a hearing scheduled for 2027 or 2028.

United StatesLitigation, Mediation & Arbitration

What to Know

  • An ICC tribunal ruled by majority that Venture Global failed to declare Calcasieu Pass operational on time.
  • Galp’s damages will be decided at a hearing in 2027 or 2028, and Venture Global says they are capped at $170 million.
  • Galp and BP won liability rulings while Shell and Repsol lost, so LNG contract terms need individual review.

Galp has secured a favourable liability ruling in its dispute with Venture Global over the Calcasieu Pass LNG liquefaction facility in Louisiana. The disputes concern when deliveries should have commenced under long-term LNG sale and purchase agreements (LNG SPAs), an issue we explored in our 2024 chapter, ‘LNG Delivery Disputes’, in the Fourth Edition of Liquefied Natural Gas: The Law and Business of LNG.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from