ARTICLE · 12 NOVEMBER 2020

Update On Colombia's Bid Process For Pacific LNG Import Terminal And Associated Transport Infrastructure

A&O Shearman
A&O Shearman
Contributor

A&O Shearman

Introducing A&O Shearman Unparalleled global depth for a changing world. Today more than ever,...

View firm profile
Explore more from A&O Shearman

Following our previously published Client Alert titled, "Colombia Relaunches Bid Process for Pacific LNG Import Terminal and Associated Transport Infrastructure," ("Previous Client Alert")...

United StatesEnergy and Natural Resources

Following our previously published Client Alert titled, " Colombia Relaunches Bid Process for Pacific LNG Import Terminal and Associated Transport Infrastructure," ("Previous Client Alert") on October 29, 2020, the Mining and Energy Planning Agency (UPME) released the final version of the tender documents for the USD 700 million LNG regasification facility and related pipeline project, commonly known as Pacific LNG ("the Project"). The revised and final version of the tender documents includes a new timeline for the development of the Project, but did not provide greater clarity on some of the more sensitive issues related to this strategic Project for Colombia.

Under the final version of the tender documents1 UPME pushed back the deadline to submit bids by two months and the deadline to complete the Project by more than two years. The most notable milestones now being as follows:

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from