The Latest On Natural Gas Force Majeure Provisions

Hogan Lovells Cadwalader
Hogan Lovells Cadwalader
Contributor
Hogan Lovells Cadwalader

Hogan Lovells Cadwalader

Hogan Lovells Cadwalader is a global law firm trusted by clients to deliver on complex, high-stakes...

View firm profile
Explore more from Hogan Lovells Cadwalader

The Superior Court of New Jersey ruled that Eni Petroleum US LLC cannot rely on a force majeure provision to excuse its obligation to deliver a certain quantity of natural gas.

United StatesEnergy and Natural Resources

In a ruling of significant importance for those confronting force majeure issues in natural gas trades, and a win for Hess Corp., the Superior Court of New Jersey, Appellate Division ruled that Eni Petroleum US LLC cannot rely on a force majeure provision in its North American Energy Standards Board ("NAESB") base contract to excuse its obligation to deliver a certain quantity of natural gas at a specified delivery point where the:

  • Transaction confirmation did not specify a particular source for the gas that defendant would provide;
  • Transaction confirmation did not specify a particular transporter to be utilized for each delivery; and
  • Delivery point specified in the transaction confirmation, which was fed by a number of different sources, remained open and unaffected by the events that caused the alleged force majeure.1