Recent Regulatory Developments In The Mexican Power Sector—Chapter 2: The Tug Of War Continues

A&O Shearman
A&O Shearman
Contributor

A&O Shearman

Introducing A&O Shearman Unparalleled global depth for a changing world. Today more than ever,...

View firm profile
Explore more from A&O Shearman

As a follow-on to our May 27, 2020 note "Recent Regulatory Developments in the Mexican Power Sector"

United StatesEnergy and Natural Resources

As a follow-on to our May 27, 2020 note " Recent Regulatory Developments in the Mexican Power Sector" (referred to hereinafter as "Chapter 1"), this note highlights further developments in the escalating clash between the administration of President Andrés Manuel López Obrador (hereinafter, the "AMLO Administration") and wind and solar generation companies—in particular, those that hold power purchase agreements awarded in the first, second and third power auctions conducted by the National Center for Energy Control of Mexico (Centro Nacional de Control de Energía-CENACE).

On April 29, 2020, CENACE issued a Resolution to Guarantee the Efficiency, Quality, Reliability, Continuity and Stability of the National Electric Grid of Mexico during the SARS-CoV2 Virus (COVID-19) Epidemic (sic)1 (the "CENACE Resolution"), which implemented temporary technical and operational measures purportedly to mitigate the effects of the COVID-19 pandemic on the National Electrical Grid

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from