ARTICLE · 04 NOVEMBER 2021

PJM's New ‘Focused' MOPR Goes Into Effect By Operation Of Law

A&O Shearman
A&O Shearman
Contributor

A&O Shearman

Introducing A&O Shearman Unparalleled global depth for a changing world. Today more than ever,...

View firm profile
Explore more from A&O Shearman

PJM Interconnection Inc.'s (PJM) new "Focused" Minimum Offer Price Rule (MOPR) went into effect on September 29, 2021, by operation of Section 205 of the Federal Power Act (FPA)...

United StatesEnergy and Natural Resources

PJM Interconnection Inc.'s (PJM) new "Focused" Minimum Offer Price Rule (MOPR) went into effect on September 29, 2021, by operation of Section 205 of the Federal Power Act (FPA), because the Federal Energy Regulatory Commission (FERC) was divided two (Chairman Glick and Commissioner Clements) against two (Commissioners Danly and Christie)1 as to the lawfulness of PJM's proposed tariff change2 and, consequently, no order was issued by FERC in response to PJM's filing.3

In October, the Commissioners issued statements, required under Section 205(g) of the FPA, explaining their views with respect to PJM's Focused MOPR.4

PJM's New 'Focused MOPR'

On July 30, 2021, PJM filed revisions to its Open Access Transmission Tariff (Tariff) to reform the application of its MOPR.5 Under PJM's Tariff filing, starting with the 2023/2024 Delivery Year, PJM will replace the "Expanded MOPR" approved by FERC in 2019,6 with a Focused MOPR that applies to all generation resource

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from