Share on LinkedInShare on LinkedIn

ARTICLE · 19 MARCH 2018

Natural Gas Act Preempts Local Efforts To Preclude Construction Of Compressor Station

Dickinson Wright PLLC
Dickinson Wright PLLC
Contributor
Dickinson Wright PLLC

Dickinson Wright PLLC

Dickinson Wright is a full-service law firm with more than 550 lawyers, serving clients across the...

View firm profile
Explore more from Dickinson Wright PLLC

As the recent decision in Algonquin Gas Transmission, LLC v. Weymouth Conservation Commission illustrates...

United StatesEnergy and Natural Resources

As the recent decision in Algonquin Gas Transmission, LLC v. Weymouth Conservation Commission[1] illustrates, local units of government have limited options to foreclose the siting of natural gas pipelines and appurtenances. The Natural Gas Act (the "NGA") provides FERC broad preemptive authority to site natural gas facilities, with only a few enumerated exceptions.[2]

On October 22, 2015, Algonquin Gas Transmission, LLC ("Algonquin") and Maritimes & Northeast Pipeline, LLC ("Maritimes") filed an application for a Certificate of Public Convenience and Necessity with the Federal Energy Regulatory Commission ("FERC"), seeking regulatory approval of their Atlantic Bridge natural gas pipeline project (the "AB Project"). As a part of the AB Project, Algonquin sought to construct a compressor station (the "Weymouth Compressor Station") in the town of Weymouth, Massachusetts (the "Weymouth") on land near the Fore River currently owned by Algonquin and on which Algonquin

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.