Nationwide Permit 12 Temporarily Revived, But Keystone XL Remains Stalled

On July 6, 2020, the United States Supreme Court temporarily revived the use of the U.S. Army Corps of Engineers' Nationwide Permit 12 to construct new oil and gas pipelines across waterways, ...

United StatesEnergy and Natural Resources
Taft Stettinius & Hollister LLP
Taft Stettinius & Hollister LLP
Author LinkedIn connections

On July 6, 2020, the United States Supreme Court (Supreme Court) temporarily revived the use of the U.S. Army Corps of Engineers' (Corps) Nationwide Permit (NWP) 121 to construct new oil and gas pipelines across waterways, but explicitly excluded the Keystone XL pipeline from its ruling. The one-paragraph order, without explanation or noted dissent, stayed an earlier federal district court decision that vacated NWP 12 pending an appeal to the Ninth Circuit.

Environmental groups challenged NWP 12 as it related to the Keystone XL pipeline, arguing that the permit threatened endangered species. On April 15, 2020, the District of Montana concluded that the Corps' reissuance of NWP 12 in 2017 for the Keystone XL pipeline was arbitrary and capricious and violated the Endangered Species Act (ESA). The district court vacated NWP 12 for all infrastructure projects and remanded it to the Corps to complete consultations with the U.S. Fish and Wildlife Service and the National