Share on LinkedInShare on LinkedIn

ARTICLE · 15 APRIL 2008

Interconnection Overhaul Overdue

Bracewell LLP
Bracewell LLP
Contributor
Bracewell LLP

Bracewell LLP

Paris is a vital energy hub in Europe, and our Paris office plays a central role in helping address...

View firm profile
Explore more from Bracewell LLP

First-come, first-served rules governing interconnection to the high-voltage transmission grid are keeping generation off-line that is needed to serve load, meet capacity reserve requirements and satisfy renewable portfolio standards that have been adopted in a growing number of jurisdictions.

United StatesEnergy and Natural Resources
Bracewell LLP
Bracewell LLP

Originally published in Electric, Light and Power, March/April 2008.

First-come, first-served rules governing interconnection to the high-voltage transmission grid are keeping generation off-line that is needed to serve load, meet capacity reserve requirements and satisfy renewable portfolio standards that have been adopted in a growing number of jurisdictions. Those rules also tend to make the cost of interconnecting a moving target as projects enter and exit interconnection study queues, complicating the financing of needed new generation.

The rules' author—the Federal Energy Regulatory Commission in Order No. 2003—recently announced that the industry should not expect relief from the current interconnection rules except through case-by-case exceptions. That is unfortunate, as an industry-wide overhaul of interconnection basics is in order.