ARTICLE · 10 OCTOBER 2025

FERC Fines Electric Utility For Providing False Information To NERC Regional Entity

Baker Botts L.L.P.
Baker Botts L.L.P.
Contributor
Baker Botts L.L.P.

Baker Botts L.L.P.

Baker Botts is a leading international law firm with 11 offices located in the US, Europe, and the...

View firm profile
Explore more from Baker Botts L.L.P.

On October 2, 2025, the Federal Energy Regulatory Commission (FERC) approved a settlement with the Los Angeles Department of Water and Power (LADWP) to resolve an Office of Enforcement (Enforcement)...

United StatesEnergy and Natural Resources

On October 2, 2025, the Federal Energy Regulatory Commission (FERC) approved a settlement with the Los Angeles Department of Water and Power (LADWP) to resolve an Office of Enforcement (Enforcement) investigation of LADWP's failure to comply with the North American Electric Reliability Corporation's (NERC) Rules of Procedure (ROP) by providing false information in an audit. LADWP agreed to pay a civil penalty of $350,000 and to submit annual compliance monitoring reports for several years in resolution of the investigation.

FERC's approval of the settlement marks a rare instance of a civil penalty assessment for failure to provide accurate information to a regional entity in a NERC audit. The settlement affirms NERC's broad audit and enforcement authority and reflects the importance FERC places on accurate and complete communications with NERC and regional entities. The settlement also emphasizes that responsibility rests with the NERC-regulated entity to ensure

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from