Court Of Federal Claims Decision Offers Potential Recovery Opportunity For Energy Savings Performance Contracts And Task Order Bid Protests

Crowell & Moring LLP
Crowell & Moring LLP
Contributor
Crowell & Moring LLP

Crowell & Moring LLP

Crowell & Moring’s Doha office is a full service legal practice that serves as the firm’s regional...

View firm profile
Explore more from Crowell & Moring LLP

A recent Court of Federal Claims decision addressed a novel fact pattern involving a bid protest (seeking bid preparation costs) relating to an energy savings performance...

United StatesEnergy and Natural Resources

A recent Court of Federal Claims decision addressed a novel fact pattern involving a bid protest (seeking bid preparation costs) relating to an energy savings performance contract (ESPC) and has the potential to expand contractor recovery opportunities in both areas of law.

In Siemens Government Technologies, Inc. v. United States,Siemens was pursuing task orders under a Department of Energy indefinite delivery, indefinite quantity (IDIQ) ESPC for energy conservation measures (ECMs) at six overseas Navy bases. ESPCs are vehicles that allow agencies to procure ECMs with little to no up-front capital costs, as the ECM installation costs are typically financed and paid back over the course of the contract (which can last up to 25 years) through the cost savings generated by the project. ESPC projects commonly consist of five phases: (1) acquisition planning; (2) contractor selection and preliminary assessment; (3) project development; (4) project implementation & const

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from