GAO's key personnel rule is well-known—and often a source of frustration— amongst government contractors.

United StatesEmployment and HR

GAO's key personnel rule is well-known—and often a source of frustration— amongst government contractors. Proposed key personnel who become "unavailable" prior to contract award—especially where they have accepted employment with a different company—may doom an offeror's proposal by rendering it noncompliant with solicitation requirements. But GAO's recent decision inFYI – For Your Information, Inc., B-423774, B-423774.2 (Dec. 19, 2025)provides some potential relief from that rule.

InFYI, the protester alleged that the awardee's proposed program manager—a key personnel requirement—had accepted employment with a different company and, thus, was "unavailable" prior to award, such that the awardee's proposal should have been disqualified consistent with GAO's key personnel jurisprudence. GAO rejected this argument. In so doing, GAO noted that notwithstanding his departure, the key person in question had indicated his intent to return to the awardee to perform on the

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from