An Ohio Court of Appeals recently issued a decision overturning a jury verdict that awarded a contractor $604,602 for loss of productivity caused by the project’s owner. Although the project was completed on time, the contractor claimed that errors in the project plans and specifications reduced its productivity. Yet, the Court, relying on the express language of the contract, denied the contractor’s claim. In so doing it failed to even consider an Ohio statute on this subject.
DiGioia Brothers Excavating, Inc. entered into a contract with the City of Cleveland for the installation of water mains. Cleveland hired the engineering firm of Stilson & Associates to prepare the plans and specifications for the project. Stilson was required to identify the location of existing underground utilities within the project’s right-of-way. The plans prepared by Stilson identified 455 utility interferences that DiGioia would have to work around. However, the plans failed to show 26 other