Notes On A Preliminary Meeting

Today's entry reports on what was the tenth preliminary meeting to be held so far under the Planning Act regime.

United KingdomStrategy

Today's entry reports on what was the tenth preliminary meeting to be held so far under the Planning Act regime.

The 'preliminary meeting' is the first (and potentially only) meeting about an application under the Planning Act 2008 regime. It is a meeting about procedure, but it is also where a sense of how the application will be approached by the various parties is established. The nearest equivalent in the town and country planning regime is the pre-inquiry meeting - but since the Planning Act has no scope for an inquiry, it isn't called that. The day after the preliminary meeting, the maximum of six months for examining the application starts.

Last Thursday I attended my second preliminary meeting (PM), but my first as the advocate of the promoter. This was for the first application for harbour facilities under the Planning Act, being made by Able Humber Ports Ltd and took place at Immingham Civic Centre on Humberside. Here is a report of the meeting although

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from