Today's entry reports on what was the tenth preliminary
meeting to be held so far under the Planning Act regime.
The 'preliminary meeting' is the first (and potentially
only) meeting about an application under the Planning Act 2008
regime. It is a meeting about procedure, but it is also where a
sense of how the application will be approached by the various
parties is established. The nearest equivalent in the town and
country planning regime is the pre-inquiry meeting - but since the
Planning Act has no scope for an inquiry, it isn't called that.
The day after the preliminary meeting, the maximum of six months
for examining the application starts.
Last Thursday I attended my second preliminary meeting (PM), but
my first as the advocate of the promoter. This was for the first
application for harbour facilities under the Planning Act, being
made by Able Humber Ports Ltd and took place at Immingham Civic
Centre on Humberside. Here is a report of the meeting although