This is entry number 301, published on 1 December 2011, of a
blog on the Planning Act 2008 infrastructure planning and
authorisation regime. Click
here for a link to the whole blog. If you would like to be
notified when the blog is updated, with links sent by email, click
here.
Today's entry reports on the coming into force of the first
Community Infrastructure Levy.
What would Robin Hood make of it? Today, Newark and Sherwood
District Council becomes the first local authority in the country
with a Community Infrastructure Levy (CIL) in force.
CIL is intended to be a more transparent charge on new
developments for infrastructure, previously decided on a
case-by-case basis via agreements under s106 of the Town and
Country Planning Act 1990. Fixed rates per metre for different
types of development in different parts of a council area are
charged according to a previously consulted upon, examined and
published 'charging schedule'. It then gets spent on a list
of