Today's entry reports on a decision to accept changes to the
Hinkley Point C application.
In contrast to the refusal to allow changes to Covanta
Energy's proposed Brig y Cwm energy from waste project
application last August, the Planning Inspectorate (PINS) has
allowed changes to be made to EDF's proposed Hinkley Point C
(HPC) nuclear power station application.
In a letter
issued last week, Andrew Phillipson, the chair of the now
five-person panel of what we must now call 'Examining
Inspectors', has allowed the application to continue with
changes sought at the preliminary meeting on 21 March and
elaborated upon on 30 March.
What are the changes, and why have they been allowed? The
changes are described in Table 3 in this document, starting on page 7. There are
six changes. The first is a new culvert to allow otters to cross
the Cannington Bypass at Mill Stream (all together now: awww!). The
other five changes are all to the designs of road accesses