Under most formal contracts it is necessary for the contractor to give notice of various matters before becoming entitled to extensions of time and loss and expense.

United KingdomReal Estate and Construction

Under most formal contracts it is necessary for the contractor to give notice of various matters before becoming entitled to extensions of time and loss and expense. As Jeremy Glover discusses, depending on its terms, such a provision may be treated as a condition precedent which if not followed could mean you lose your right to make a claim.

It is fair to say that, increasingly notices clauses are expressed as conditions precedent. In other words, a failure to comply with the requirements of the clause will result in a party being prevented from making what might otherwise be a perfectly valid claim.

The traditional view at common law

Generally, in the UK the courts will take the view that timescales in construction contracts are directory rather than mandatory,[1] unless that is, the contract clause in question clearly states that the party with a claim will lose the right to bring that claim if it fails to comply with the required timescale. In the case of Bre