Disclosure can often be a complex and costly milestone in any
dispute, irrespective of the relative value and complexity of the
dispute itself.
Differing disclosure obligations arise at different points in
time, whether by virtue of the CPR, court order or pursuant to a
clause in a particular contract. The notion of "putting your
cards on the table, face up", as envisaged by the Disclosure
Pilot, is in general terms commendable, and goes a long way to
reducing the need for interim applications.
However, and rightly or wrongly, it does front load litigation
costs. The recent case of Equipe Regeneration Limited v
Higgins Construction Limited & Others [2020] is a
prime example of a party's failure to understand when
disclosure obligations arise. It concerns an interim application
for specific performance for disclosure and acts as a useful
reminder to litigants as to when and how disclosure obligations can
arise.