ARTICLE · 23 JANUARY 2007
The CIC’s Adjudication Rules Are Invalid And Others May Be Too
CMS Cameron McKenna Nabarro Olswang
On Friday the Technology and Construction Court held that paragraph 25 of the latest edition of the Construction Industry Council's Model Adjudication Procedure (MAP) is invalid. Paragraph 25 (which appears in all three editions of MAP) says that a late adjudicator’s decision is effective if reached before the dispute is referred to a replacement adjudicator.
United KingdomReal Estate and Construction