Today's entry reports on the proposals for bringing into
force the infrastructure provisions of the Growth and
Infrastructure Bill.
The government's intentions as to how the Growth and
Infrastructure Bill will be brought into force have been revealed
in correspondence from the Planning Inspectorate (PINS), and they
will disappoint some project promoters.
Special parliamentary procedure (SPP) is a post-consent process
that applies to some applications under the Planning Act 2008.
The triggers for SPP, and the scope of parliamentary
consideration once it gets there, are to be reduced by the Growth
and Infrastructure Act 2013, still on course to be enacted in
April.
That's just as well, because the first application to be
consented under the Planning Act, on 13 October 2011, is still
stuck in Parliament. The next (and it is hoped, last) meeting
of the committee of
three MPs and peers examining the Rookery South Development
Consent Order is on 13 February,