ARTICLE · 12 FEBRUARY 2013

SPP To Continue To Apply To Live Applications

A discussion on the proposals for bringing into force the infrastructure provisions of the Growth and Infrastructure Bill.

United KingdomReal Estate and Construction

Today's entry reports on the proposals for bringing into force the infrastructure provisions of the Growth and Infrastructure Bill.

The government's intentions as to how the Growth and Infrastructure Bill will be brought into force have been revealed in correspondence from the Planning Inspectorate (PINS), and they will disappoint some project promoters.

Special parliamentary procedure (SPP) is a post-consent process that applies to some applications under the Planning Act 2008.  The triggers for SPP, and the scope of parliamentary consideration once it gets there, are to be reduced by the Growth and Infrastructure Act 2013, still on course to be enacted in April.

That's just as well, because the first application to be consented under the Planning Act, on 13 October 2011, is still stuck in Parliament.  The next (and it is hoped, last) meeting of the committee of three MPs and peers examining the Rookery South Development Consent Order is on 13 February,