The aim of this Protocol (drafted by the SCL and issued November 2001) is to tackle confusion over how to work out entitlements to extensions of time (EOTs) and compensation for other time-related delays. The Protocol takes the form of a 70-page guidance note, which can be downloaded from www.eotprotocol.com. The website also contains a brief summary of the terms. The document is still in draft, the consultation period being extended until 28 February 2002.
It is an extremely helpful paper which is likely to have far-reaching effects. Its raison d’etre is that it will assist all parties to the construction process when dealing with time/delay matters, by establishing "best practice" guidelines which can be referred to, pre-contract, during the lifetime of the contract, and in the event that a dispute arises. A key aspect of the Protocol is its recognition that "transparency of information and methodology is central to both dispute prevention and dispute resolution" and will avoid