Rights of Light: "Let That Be A Lesson to You..."

The case of HKRUK II (CHC) Limited v- Heaney [2010] PLS CS 238 demonstrates that developers should take care to resolve rights of light issues at the outset of a development or risk paying the ultimate price.

United KingdomReal Estate and Construction
Charlotte Wormstone
Charlotte Wormstone
Andrew Walker
Andrew Walker

The case of HKRUK II (CHC) Limited v- Heaney [2010] PLS CS 238 demonstrates that developers should take care to resolve rights of light issues at the outset of a development or risk paying the ultimate price.

HKRUK II (CHC) Limited (the "Developer") purchased a commercial building with planning for two extra floors.  Adjacent to the site was a listed building, owned by Heaney, whose rights of light were likely to be interfered with by the development.  The Developer knew this and had negotiated a reduction in the purchase price to cover any such claims.  The parties entered negotiations on the issue but reached no settlement.  The Developer commenced works in June 2008 and finished in July 2009.  In August 2009 the Developer sought a ruling that Heaney's loss could be compensated by a small award of damages.  Heaney counter-claimed for an injunction requiring demolition, which the Developer argued was oppressive.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from