Share on LinkedInShare on LinkedIn

ARTICLE · 02 JULY 2025

New Resolution Process For Building Safety Claims In The TCC And FTT

Devonshires Solicitors LLP
Devonshires Solicitors LLP
Contributor
Devonshires Solicitors LLP

Devonshires Solicitors LLP

Recognised as industry leaders, with roots that date back to 1841, we have a deep understanding of...

View firm profile
Explore more from Devonshires Solicitors LLP

The Building Safety Act Working Group announced on Friday 20 June 2025 that it intends to introduce a new streamlined resolution process for building safety related claims under the Building Safety Act 2022...

United KingdomReal Estate and Construction

The Building Safety Act Working Group announced on Friday 20 June 2025 that it intends to introduce a new streamlined resolution process for building safety related claims under the Building Safety Act 2022 ("BSA") which is significant for lawyers and their clients making and defending such claims. This represents a further shaping of the new legal procedures under the BSA, and offers the prospect of procedural advantages and greater certainty.

The objective of the streamlined resolution process is to facilitate disputes in which parties may be seeking different orders under the BSA, as set out below:

  1. Remediation Order ("RO") under section 123 of the BSA;
  2. Remediation Contribution Order ("RCO") under section 124 of the BSA; and