Here the court found an implied term in a building contract to
allow it to comply with the Housing Grants, Construction and
Regeneration Act 1996 (Construction Act). The amended JCT
minor works contract provided for final payment to be made 72 hours
after receipt of an invoice. However the pay less notice
provisions had not been amended, meaning that service of a pay less
notice had to occur prior to the issue of the invoice (being 5 days
before final date for payment). When the employer
served a pay less notice on 28 October, 5 days after an invoice
issued on 23 October, the contractor started an adjudication,
claiming the notice was invalid.
The adjudicator found for the contractor, deciding that the
notice should have been served on 21 October, before the invoice
was issued. The employer issued court proceedings for a
declaration (i) that the decision was unenforceable as the
adjudicator had breached the rules of natural justice, and (ii) as
to the correct