As part of its 2016 rolling programme of updates, the Joint Contracts Tribunal (JCT) has now published the JCT 2016 Design and Build (DB) Contract family.

United KingdomReal Estate and Construction

As part of its 2016 rolling programme of updates, the Joint Contracts Tribunal (JCT) has now published the JCT 2016 Design and Build (DB) Contract family. We set out below practical tips on the new provision for Interim Valuation Dates in the core Design and Build 2016 wording.

Design and Build 2016 - Section 4: Payment

In the drafting of DB 2016, the JCT's overall intention has been to simplify the payment provisions and the wording has therefore been re-arranged into eight sections as follows:

  1. Contract Sum and Adjustments
  2. Taxes
  3. Payments and Notices - general provisions
  4. Interim Payments - calculation of sums due
  5. Listed Items
  6. Retention
  7. Loss and Expense
  8. Final Statement and Final Payment.