ARTICLE · 11 APRIL 2018

Get Out Of Jail Free? Grove Developments v S&T [2018]

Mishcon de Reya LLP
Mishcon de Reya LLP
Contributor
Mishcon de Reya LLP

Mishcon de Reya LLP

Founded by Lord Mishcon in 1937, in a one-room office in Brixton, Mishcon de Reya now employs over...

View firm profile
Explore more from Mishcon de Reya LLP

The recent TCC decision has sent shockwaves through the construction industry. In summary, it has established that if a paying party under a construction contract fails to issue a valid pay less...

United KingdomReal Estate and Construction

The recent TCC decision has sent shockwaves through the construction industry. In summary, it has established that if a paying party under a construction contract fails to issue a valid pay less notice in relation to an interim payment, they may commence adjudication in order to determine the true value of the payment to be made under the relevant payment notice. This has the potential to radically alter the tactics of a payment dispute under a construction contract.

Facts

Under the terms of a JCT Design & Build Contract 2011, Grove Developments ("Grove") retained S&T to design and construct a Premier Inn Hotel at Heathrow Terminal 4.

Following Practical Completion there were three adjudications. The third adjudication concerned the validity of Grove's pay less notice in respect of the final interim payment.