Story resisted Supablast’s attempts to enforce an adjudicator’s decision on the grounds that the adjudicator did not have jurisdiction to decide the final account dispute as there were two contracts for the works, one for the blasting, painting and scaffolding and another for steelwork.

United KingdomReal Estate and Construction

Originally published in Dispatch, March 2010
Dispatch highlights a selection of the important legal developments during the last month

Supablast (Nationwide) Ltd v Story Rail Ltd
[2010] EWHC 56 TCC

Story resisted Supablast's attempts to enforce an adjudicator's decision on the grounds that the adjudicator did not have jurisdiction to decide the final account dispute as there were two contracts for the works, one for the blasting, painting and scaffolding and another for steelwork. Story argued that the adjudicator had been asked to decide more than one dispute in relation to two contracts. The works at the centre of the dispute were in relation to the substantial refurbishment of a railway bridge known as Carr Mill Viaduct in St Helens, Merseyside. The first time the two contracts point emerged was within Story's Response in the adjudication proceedings. As far as Supablast were concerned there was a single agreement and all elements of the works were covered by