Construction contracts often include provisions for adjudication, a dispute resolution mechanism designed to provide quick interim decisions. But what happens when one party fails to pay the adjudicator's fees, and can the adjudicator's decision still be enforced? Recent case law examines the validity of adjudication decisions when payment obligations remain unfulfilled.

United KingdomReal Estate and Construction

The essence of the principle established in S&T (UK) Ltd v Grove Developments Ltd [2018] EWCA Civ 2448 is well understood. Where the statutory payment regime produces a notified sum, the payer must pay that sum before commencing an adjudication designed to establish the ‘true value’ of the relevant account. The policy underpinning the Housing Grants, Construction and Regeneration Act 1996 is clear: cash flow takes priority over valuation disputes.

This applies even if there is no adjudication decision regarding the notified sum: AM Construction v The Darul Amaan Trust [2022] EWHC 1478 (TCC).

What Grove did not resolve, however, was the scope of that prohibition. Does it apply to all adjudications or just ones regarding the same payment cycle? Does it only apply to conventional true valuation adjudications, or can it extend to disputes concerning defects and delay?

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from