This months top tip - December

Welcome to the first edition of our Contractor monthly bulletin, a practical tip per month focussing on process and application issues for contract administrators.

We hope you find this useful and we do value your feedback so please feel free to contact us if you have any comments.

Pay less notices

  • Pay less notices have replaced withholding notices for all construction contracts entered into after 1 October 2011.
  • The Pay less notice is only issued if there is a notified sum.
  • The Pay less notice must be issued within the time period agreed in the construction contract.

Before the 1 October 2011, withholding notices stated the amount proposed to be withheld and the proposed grounds for withholding. This has changed. Pay less notices must state the sum the payer considers will become due on the date the notice is served and the basis on which that sum is calculated.