This months top tip - December
Welcome to the first edition of our Contractor monthly bulletin,
a practical tip per month focussing on process and application
issues for contract administrators.
We hope you find this useful and we do value your feedback so
please feel free to contact us if you have any comments.
Pay less notices
- Pay less notices have replaced withholding notices for all
construction contracts entered into after 1 October 2011.
- The Pay less notice is only issued if there is a notified
sum.
- The Pay less notice must be issued within the time period
agreed in the construction contract.
Before the 1 October 2011, withholding notices stated the amount
proposed to be withheld and the proposed grounds for withholding.
This has changed. Pay less notices must state the sum the payer
considers will become due on the date the notice is served and the
basis on which that sum is calculated.