ARTICLE · 19 MARCH 2026

When "No Later Than" Is Not Enough: Calver J On Refund Guarantees, Conditions, Innominate Terms And Commercial Common Sense

Quadrant Chambers
Quadrant Chambers
Contributor
Explore more from Quadrant Chambers

In SLB and others v PAK and others [2026] EWHC 449 (Comm), handed down on 2 March 2026, the Commercial Court has confirmed that a shipyard's obligation...

United KingdomLitigation, Mediation & Arbitration

OVERVIEW

In SLB and others v PAK and others  [2026] EWHC 449 (Comm), handed down on 2 March 2026, the Commercial Court has confirmed that a shipyard’s obligation to provide refund guarantees within a specified time was not a contractual condition, even in a high value and complex shipbuilding project.

Calver J dismissed the Buyers’ appeals under section 69 of the Arbitration Act 1996 and upheld 10 unanimous LMAA arbitration awards. The decision is an important reminder that, in modern English law, putting a deadline on a term is not necessarily enough to transform it into a condition carrying automatic loss of bargain consequences, particularly where there is an express cancellation right contingent upon the passage of that deadline.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from