Vinergy International (PVT) Ltd v Richmond Mercantile Ltd FZC (2016)

Court of Appeal finds that a party did not have to give notice before terminating the contract for repudiatory breach.

United KingdomLitigation, Mediation & Arbitration

Court of Appeal finds that a party did not have to give notice before terminating the contract for repudiatory breach

In this decision, again highlighting the benefit of precise drafting, the Court of Appeal decided that the respondent, Richmond Mercantile Ltd (a manufacturing company), was able to terminate an agreement for repudiatory breach without complying with the notice and remedy requirements in the contract's termination clauses.

The appellant, Vinergy International (PVT) Ltd (a chemical distribution company), had entered an agreement with Richmond for the supply of bitumen for an extendable term of 10 years.  Clauses 17 and 18 concerned termination and provided that either party could terminate the agreement immediately upon failure to observe its terms and remedy them "where..capable of being remedied within the period specified in the notice given by the aggrieved party to the party in default" (clause 17.1.1)