The UK Supreme Court has recently confirmed an important
principle regarding the application of liquidated damages clauses.
In Triple Point Technology, Inc v PTT Public Company
Ltd,1 the Supreme Court confirmed that, as a
general rule, liquidated damages will continue to accrue until such
time as the parties' contract is terminated, irrespective of
whether the work on the contract was ever completed. In reaching
this conclusion, the Supreme Court overturned a decision of the
Court of Appeal that held to the contrary – that liquidated
damages did not accrue in respect of work that was never
completed.
The Supreme Court's decision will be of particular
interest to parties to construction contracts, given the central
role played by liquidated damages for delay in managing the
parties' relationship under such contracts.