The Availability Of Anti-Suit Relief, Despite Delay (Specialised Vessel Services Ltd v MOP Marine Nigeria Ltd)

Quadrant Chambers
Quadrant Chambers
Contributor
Explore more from Quadrant Chambers

The acknowledged starting point when seeking anti-suit injunctive relief is you must act promptly, but is that the whole story?

United KingdomLitigation, Mediation & Arbitration

This article was first published by Lexis®PSL on 24 February 2021.

Mini-summary

The acknowledged starting point when seeking anti-suit injunctive relief is you must act promptly, but is that the whole story? In a case where a party waited approximately a year to bring a claim for injunctive relief to the English High Court, Mr Justice Calver granted it. The case highlights the factors on which a party can rely to counter an argument that there has been delay. The case also considers the effect on the exercise of the Court's discretion of the Defendant having obtained an injunction abroad in breach of an exclusive arbitration agreement.

Specialised Vessel Services Ltd v MOP Marine Nigeria Ltd [2021] EWHC 333 (Comm)