This case considered an application for summary judgment and/or
strike out of the whole or part of a claim by NHBC and looked into
whether the property owner could recover the cost of remedial
works.
The claimant's bungalow was constructed by a contractor with
the benefit of NHBC Buildmark cover. When defects became apparent,
the claimant gained a partial award via arbitration against the
contractor which he failed to pay.
The claimant later began a second arbitration against the
contractor which deemed to be rather problematic as the latter was
in the process of liquidation. It became apparent that the NHBC
policy would be the claimant's main source of compensation and
as such the claimant and NHBC entered into a settlement agreement
whereby the second arbitration was discontinued and NHBC agreed to
consider any claims that had not been addressed in the first
arbitration to the extent that they fell within the scope of the
NHBC policy.