Judge Wrong To Refuse Permission To Amend And Relief From Sanction For Late Cost Budget (Right Support Management Limited V The London Borough Of Hillingdon)

Gatehouse Chambers
Gatehouse Chambers
Contributor
Gatehouse Chambers

Gatehouse Chambers

Gatehouse Chambers is a leading commercial set with expertise spanning commercial dispute...

View firm profile
Explore more from Gatehouse Chambers

Dispute Resolution analysis: On appeal, Ritchie J has concluded that permission ought to have been granted to a Claimant who sought to amend its Particulars of Claim and that relief should...

United KingdomLitigation, Mediation & Arbitration

Dispute Resolution analysis: On appeal, Ritchie J has concluded that permission ought to have been granted to a Claimant who sought to amend its Particulars of Claim and that relief should have been granted from the usual, harsh sanction imposed by CPR r.3.14 for the very late filing of a cost budget. However, a less draconian sanction was imposed instead.

Right Support Management Limited v The London Borough of Hillingdon [2025] EWHC 1680 (KB)

What are the practical implications of this case?

This judgment represents an innovative approach to the question of relief from sanctions which is of historical legal interest not least because it concerns the sanction imposed by CPR r.3.14, CPR. Such is the draconian nature of the sanction imposed by that provision, this judgment has concluded on appeal that relief ought to have been granted despite the cost budget being filed and served more than 2 years late. This decision was taken by reference to various factors

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.