High Court Finds Liquidated Damages Clause For Delay In Construction Contract Was Not Unlawful Penalty

The High Court has found that clauses in engineering, procurement and construction (EPC) contracts relating to solar power plants, which provided for a delay damages rate of £500 per day per MWp,

United KingdomLitigation, Mediation & Arbitration

The High Court has found that clauses in engineering, procurement and construction (EPC) contracts relating to solar power plants, which provided for a delay damages rate of £500 per day per MWp, were enforceable liquidated damages clauses: GPP Big Field LLP v Solar EPC Solutions SL [2018] EWHC 2866 (Comm).

Applying the Supreme Court's recast penalties test from Cavendish Square Holding BV v Talal El Makdessi [2015] UKSC 67 (considered here), the court rejected the contractor's argument that the clauses were unenforceable as penalties. It found that the provisions did not exceed a genuine pre-estimate of loss, and that the sums were not in any way extravagant or unconscionable in comparison with the legitimate interest of the employer in ensuring timely performance of the contracts.

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

See more popular content from