The Court of Appeal has held, by a majority, that a shipowner
was not entitled to rely on a force majeure clause in a shipping
contract where its charterer's parent company became subject
to US sanctions: MUR Shipping BV v RTI Ltd [2022] EWCA
Civ 1406.
The decision turned on the wording of the force majeure clause,
which required that the force majeure event could not be
“overcome by reasonable endeavors” on the part of the
affected party. The High Court had held that, in exercising
reasonable endeavours, the shipowner was not obliged to accept
anything other than contractual performance (see our post on that decision).
The Court of Appeal disagreed, finding that the clause required
the shipowner to accept a proposal involving payment in an
alternative currency, which did not extend to full contractual
performance, but which achieved precisely the same result as it:
(i) fulfilled the underlying purpose of the relevant obligation;
and (ii) caused no detriment to the