This article reports on a judgment of the High Court in relation
to a dispute between a Saudi-based company, Selevision Saudi Co
(SSC), and a Qatari-based company, Bein Media Group LLC (BMG), both
of which operate in the broadcasting sector. This judgment
clarified the effect of Civil Procedure Rule (CPR) 62.18 and the
extent to which it imported the provisions of CPR 8 into an action
to enforce an arbitral award made in a foreign jurisdiction. The
judgment also contained guidance on the enforcement of such awards,
and the circumstances in which the Court may grant a stay of
enforcement of them.
Origins of the dispute
This dispute arose out of an arbitration between these two
parties which was conducted in Qatar. The arbitrators had found
that BMG was liable to pay SSC over $8 million (USD) for its
breaches of a Distribution Agreement, but BMG did not honour this
award.