The English common law trend of allowing the recovery of damages
for rectification of defects even where the defects liability
period remains ongoing has been followed in a recent judgement from
the High Court of Singapore in Thio Keng Thay v Sandy Island Pte Ltd
[2019] SGHC 175. It is likely this approach would be mirrored
by the Scottish and English courts and so this decision serves as a
valuable reminder to UK-based employers that if they unreasonably
prevent the contractor from carrying out rectification, and engage
an alternative contractor to carry out the works, the quantum of
damages recoverable will be limited.
Facts
Thio Keng Thay (the plaintiff) purchased a luxury residential
property from Sandy Island Pte Limited (the defendant). After
taking possession of the property, the plaintiff discovered a total
of 492 alleged defects, including significant water damage, of
which approximately 200 were accepted by the defendant. The
plaintiff elected to employ a