ARTICLE · 25 MAY 2026

Eiger v Ridge: A Cautionary Tale Worth £2.5 Million

Gatehouse Chambers
Gatehouse Chambers
Contributor
Gatehouse Chambers

Gatehouse Chambers

Gatehouse Chambers is a leading commercial set with expertise spanning commercial dispute...

View firm profile
Explore more from Gatehouse Chambers

A recent High Court decision examines the liability of project monitoring surveyors in construction lending, establishing stricter standards for independence and conflicts of interest. The case explores how far a project monitor's duty extends when advising lenders on development viability, and what losses they can be held responsible for when projects fail.

United KingdomLitigation, Mediation & Arbitration

Introduction

There is a developing body of case law in relation to project monitoring surveyors (as distinct from project managers) who are typically appointed by funders and lenders in the context of construction developments.

Prior to the most recent exposition of negligence claims against project monitors in Eiger Funding (PCC) Limited v Ridge and Partners LLP [2026] EWHC 609 (TCC) (“Eiger Funding”), the courts have considered the scope of a project monitor’s liability in three principal decisions: Bank of Ireland v Faithful & Gould Ltd [2014] EWHC 2217 (TCC), Lloyds Bank plc v McBains Cooper Consulting Ltd [2018] EWCA Civ 452 and Bank of Ireland v Watts Group plc [2017] EWHC 1667 (TCC).

We operate a free-to-view policy, asking only that you register in order to read all of our content. Please login or register to view the rest of this article.

The content of this article is intended to provide a general guide to the subject matter. Specialist advice should be sought about your specific circumstances.

See more popular content from